~Business & Science Building~
Kickoff - completed
Space Requirements
- completed
Building Survey
- completed
Electronics - installed
Data/Voice/Video wiring
- completed
Smart Classroom
or other Special Issues - pending (Rooms 116/106 remodeling)
I.P. address space / VLAN organization -
complete 4.27.2001
V-LAN grouping
- complete
Cut-Over day
- May 10 -11 complete
~Armitage Hall~
Space Requirements
- completed
Building Survey
- completed
Electronics - installed
Data/Voice/Video wiring
- completed
Smart Classroom
or other Special Issues - completed
I.P. address space / VLAN organization -
completed
Cut-Over day
- completed
~Science Building~
Kickoff - Winter
2001
Space Requirements
- completed
Building Survey
- completed
Electronics - pending
Data/Voice/Video wiring
- completed
Smart Classroom
or other Special Issues - no issues
I.P. address space / VLAN organization -
pending
Cut-Over day
- pending Summer 2002
~Fine Arts Building~
Kickoff - April
18 2001
Space Requirements
- complete
Building Survey
- complete
Electronics -
pending
Data/voice/video
- pending
Smart Classroom
or other Special Issues - pending
I.P. address space / VLAN organization -
pending
Cut-Over day
- pending (Spring 2002)
~Campus Center~
Kickoff - Completed
Space Requirements
- complete
Building Survey
- complete
Electronics -
pending
Data/voice/video wiring
- complete
Smart Classroom
or other Special Issues - pending
I.P. address space / VLAN organization -
pending
Cut-Over day
- pending
~Law school~
Kickoff - Completed
Space Requirements
- complete
Building Survey
- complete
Electronics -
pending
Data/voice/video wiring
- pending (Feb 22 2002 as target)
Smart Classroom
or other Special Issues - pending
I.P. address space / VLAN organization -
pending
Cut-Over day
- pending