Camden Internal Checklist for Runet2000 Status




RUnet 2000 links

"The Transition Process"

"RUNet 2000 Application Survey Info"

RU L2/L3 mapping utility

"RUNet 2000 Application Survey Inventory"

IP Renumbering Checking Tool

"RUNet 2000 Plan for Transitioning University NetWare Servers to use IP"

"RUNet 2000 Appletalk Transition Notes"


Camden various links

Time tables for overall transition process

Ciscos' list of NIC compatablity and operational issues

VLAN information for BSB

BSB Switch numbering



Building list for Camden campus

~Business & Science Building~

Kickoff - completed

Space Requirements - completed

Building Survey - completed

Electronics - installed

Data/Voice/Video wiring - completed

Smart Classroom or other Special Issues - pending (Rooms 116/106 remodeling)

I.P. address space / VLAN organization - complete 4.27.2001

V-LAN grouping - complete

Cut-Over day - May 10 -11 complete

~Armitage Hall~

Kickoff - completed

Space Requirements - completed

Building Survey - completed

Electronics - installed

Data/Voice/Video wiring - completed

Smart Classroom or other Special Issues - completed

I.P. address space / VLAN organization - completed

Cut-Over day - completed
 
 

~Science Building~

Kickoff - Winter 2001

Space Requirements - completed

Building Survey - completed

Electronics - pending

Data/Voice/Video wiring - completed

Smart Classroom or other Special Issues - no issues

I.P. address space / VLAN organization - pending

Cut-Over day - pending Summer 2002
 
 

~Fine Arts Building~

Kickoff - April 18 2001

Space Requirements - complete

Building Survey - complete

Electronics - pending

Data/voice/video - pending

Smart Classroom or other Special Issues - pending

I.P. address space / VLAN organization - pending

Cut-Over day - pending (Spring 2002)

~Campus Center~

Kickoff - Completed

Space Requirements - complete

Building Survey - complete

Electronics - pending

Data/voice/video wiring - complete

Smart Classroom or other Special Issues - pending

I.P. address space / VLAN organization - pending

Cut-Over day - pending

~Law school~

Kickoff - Completed

Space Requirements - complete

Building Survey - complete

Electronics - pending

Data/voice/video wiring - pending (Feb 22 2002 as target)

Smart Classroom or other Special Issues - pending

I.P. address space / VLAN organization - pending

Cut-Over day - pending

















Last update 01.30.2002  JFG